Activity Finish Moving Ahead 1day

4 replies [Last post]
Ammar Tauqeer
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Hello,

There is a problem when i update the schedule and mark the activity as started my activity finish date automatically moves ahead. Example For an activity A my start date is 12.Oct.2013 and finish date is 15.oct.2013. When i update the schedule and move my data date to 13.Oct.2013 my finish date automatically moves to 16.Oct.2013 

Replies

Raymund de Laza
User offline. Last seen 8 weeks 3 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Edit... User Preferences..... Dates.... Under the Time Click the button beside the Format you wish to display Time on the Dates Columns.

Ammar Tauqeer
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Raymund de Laza from where i can manage the time of an activity?

Raymund de Laza
User offline. Last seen 8 weeks 3 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

The issue is related with Time of the day... When ever updating any activity, consider the time start and time finish of activity.

Rafael Davila
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 1 Mar 2004
Posts: 5233

For started activities if you do no change remaining duration the finish date will usually be delayed after re-scheduling run to be DD+remaining duration unless any other reason such as out-of-sequence rules takes over and delays it even further.