Planning, Scheduling & Programming Discussion Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Sun, 2011-08-07 08:18 Permalink Craig1st The difference may Craig 1st The difference may be a second 2nd (more likely) check your resource assignments; in general this error is from there. Did you schedule (F9) before? This sometimes eliminates this error. To find the activity responsible for this error, try "check project integrity". It will show that activity. If this won't work for the project, disconnect the baseline and do the same with it. By the way: Is your baseline "as built"? Good luck! Dieter Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Sun, 2011-08-07 08:18 Permalink Craig1st The difference may Craig 1st The difference may be a second 2nd (more likely) check your resource assignments; in general this error is from there. Did you schedule (F9) before? This sometimes eliminates this error. To find the activity responsible for this error, try "check project integrity". It will show that activity. If this won't work for the project, disconnect the baseline and do the same with it. By the way: Is your baseline "as built"? Good luck! Dieter
Member for
18 years 9 monthsCraig1st The difference may
Craig
1st The difference may be a second
2nd (more likely) check your resource assignments; in general this error is from there.
Did you schedule (F9) before? This sometimes eliminates this error.
To find the activity responsible for this error, try "check project integrity". It will show that activity.
If this won't work for the project, disconnect the baseline and do the same with it.
By the way: Is your baseline "as built"?
Good luck!
Dieter