P6.2.1, Baseline Query

Member for

18 years 9 months

Craig

1st The difference may be a second

2nd (more likely) check your resource assignments; in general this error is from there.

Did you schedule (F9) before? This sometimes eliminates this error.

To find the activity responsible for this error, try "check project integrity". It will show that activity.

If this won't work for the project, disconnect the baseline and do the same with it.

By the way: Is your baseline "as built"?

Good luck!

Dieter