Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6.2.1, Baseline Query

1 reply [Last post]
Craig Freake
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 17
Groups: None

Appreciate your help on this one....I am getting the following error when trying to update the Baseline with Current Actviity changes for the period...

 

2011-08-04T16:20:50 SEVERE Errors located: RemainingDuration: Remaining Duration cannot be greater than At Completion Duration.

I have reviewed all activities, no where is the RD greater than the At Completion Duration???

 

Any suggestions about what settings is required for updating Baselines??

 

Much appreciated...

 

Craig

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Craig

1st The difference may be a second

2nd (more likely) check your resource assignments; in general this error is from there.

Did you schedule (F9) before? This sometimes eliminates this error.

To find the activity responsible for this error, try "check project integrity". It will show that activity.

If this won't work for the project, disconnect the baseline and do the same with it.

By the way: Is your baseline "as built"?

Good luck!

Dieter