Your activities are starting out of sequence (per schedule logic, not perhaps site logic). You need to analyze your schedule and figure out if the relationships should not be rethought. Sometimes you cannot avoid some out of sequence works, but it should not be a whole lot of activities. If so, then works at site are going according to a different plan and either their (site) plan or your plan needs to change.
Mustansar,The activity you are updating is out of sequence. Most probably; you should have a FS predecessor to the activity that does not finished. So when you start the activity without finishing FS predecessor, primavera is continuing the remaining of the progressed activity after finishing of predecessor (which means keeping logic). This is called "Retained Logic".Regards,Safak
Your activities are starting
Your activities are starting out of sequence (per schedule logic, not perhaps site logic). You need to analyze your schedule and figure out if the relationships should not be rethought. Sometimes you cannot avoid some out of sequence works, but it should not be a whole lot of activities. If so, then works at site are going according to a different plan and either their (site) plan or your plan needs to change.
Mustansar,The activity you
Mustansar,The activity you are updating is out of sequence. Most probably; you should have a FS predecessor to the activity that does not finished. So when you start the activity without finishing FS predecessor, primavera is continuing the remaining of the progressed activity after finishing of predecessor (which means keeping logic). This is called "Retained Logic".Regards,Safak
Hi, Go the bar settings and
Hi,
Go the bar settings and for the actual bar choose current bar instead of actual bar