Hi
A Very Very Happy New Year to members of Planning Planet.
I am a young professional in Planning & have never work before either on site or on a Planning & Scheduling. My goal is to become a successful planner & I got opportunity in my current organization now. I am looking some guidance on this issue.
If any one has complete library of Manpower & machinery calculation please guide me on md.farooque@gmail.com
My project is not a big one but the items are included as follows.
1-Road Diversion
2-Relocation of existing Utilities
3-Excavation & formation preparation
4-Bedding of Material & Laying of Pipe
5-Welding of Pipe in Trench
6-Construction of Thrust Block
7-Initial Back Filling
8-Testing
9-Sterilization and cleaning
10-Final Back Filling
11-Restoration of Asphalt
Construction of Valve Chambers
1-Setting out
2-Excavation for Manhole
3-Blinding
4-Construction of Base
5-Construction of Wall
6-Installation of Fittings & Valve
7-Test
8-Cover Slab
I never worked on any pipeline project before, only worked on Railway & Highway project in Drawing & Quantity section. This project is in Saudi Arabia. I am on a junior level so I don't have information related to soil, or any other issue which may required to planning,
If you have specification of pipe line project & any design book for design of valve chamber please share with me.
Here I need manpower & machinery calculation, how much gap should be gap between each activity. I know MSP & P6 but not expert.
You can guide me on md.farooque@gmail.com
Farooque
+966-544943431
+91-9701062756