Exporting Only some Activities

Member for

19 years
Permalink

Kumar,
Filter those activities that you want to copy and do the copy and paste but make sure that both project are open (old & new) then organized (Group & Sort) by EPS/WBS.

Member for

15 years 9 months
Permalink

Dera Sir,
since i have thousands of activities inside the wbs which i am copying,is there any method to copy only some jobs which are coming in that wbs.
i have gruoped the equipment with category wise.for ex pumps.
so i want all the pumps activities only to be copied to the new project.
any suggestions...

Member for

16 years 11 months
Permalink

Hi Kumar

You can filter those activities to export and save it as layout wih WBS of desired name .Copy and paste to the palace where you need it to export

Member for

19 years
Permalink

Kumar,
Create a new project then open both project (old and new) then use WBS window and drag & drop or use cut & paste from old to new.