Kumar,
Filter those activities that you want to copy and do the copy and paste but make sure that both project are open (old & new) then organized (Group & Sort) by EPS/WBS.
Dera Sir,
since i have thousands of activities inside the wbs which i am copying,is there any method to copy only some jobs which are coming in that wbs.
i have gruoped the equipment with category wise.for ex pumps.
so i want all the pumps activities only to be copied to the new project.
any suggestions...
RE: Exporting Only some Activities
Kumar,
Filter those activities that you want to copy and do the copy and paste but make sure that both project are open (old & new) then organized (Group & Sort) by EPS/WBS.
RE: Exporting Only some Activities
Dera Sir,
since i have thousands of activities inside the wbs which i am copying,is there any method to copy only some jobs which are coming in that wbs.
i have gruoped the equipment with category wise.for ex pumps.
so i want all the pumps activities only to be copied to the new project.
any suggestions...
RE: Exporting Only some Activities
Hi Kumar
You can filter those activities to export and save it as layout wih WBS of desired name .Copy and paste to the palace where you need it to export
RE: Exporting Only some Activities
Kumar,
Create a new project then open both project (old and new) then use WBS window and drag & drop or use cut & paste from old to new.