Interruptible vs. contiguous

Member for

17 years 2 months

Hi,



Your activities should be connected to the resources. So if you have material deliveries coming in with certain frequency and the rate of completion at site is higher than the rate of supply to site you will have interrupted duration; that is once the material comes to site you can complete the activity.



Again, if you have a special person doing a certain job like commissioning of a system, then when this person at site, this activity can be ongoing.



On the other hand, excavation, concreting, steel reinforcement, block building, plastering, and most of the civil works are continuous activities.



Good luck,



Samer

Member for

19 years 1 month

i guess it’s like progress override or retained logic



(i’m just a trying hard aspiring planner by the way)