Methods of Monitoring progress

Member for

16 years 3 months
Permalink

I beleive that Edgar was the first to comment and S-Curves and EVM are stil relevant. not sure what you want to use ? 

Member for

19 years 1 month
Permalink

Well I guess it's good to resurrect this old, undying or endless issue for the benefit of everyone who maybe interested. Oh, and I was the first to comment as well. Anyway, time traveled over a decade and I guess even though technology changed very fast and mobile apps come and go like a blink of an eye, the principles for monitoring project progress hasn't changed, faded or become obsolete. So the question remains the same, but perhaps now has more choices as perhaps there were lots of sophisticated tools to use like multi-dimensional modeling and mobile technologies. Maybe S-Curves and EVM are not anymore relevant. Or maybe not?

Member for

19 years 5 months
Permalink

Norzul...based on ur explaination , that one is not fair....actually wtg based on requirment of project...example for payment.....we’ve lum sump,BQ and single item progress....based on contracts......

I’ve best progress monitoring form. from my master at Talisman rite now...
At this moment, everybody outside there using his format......

this is my email...aizamcapri@gmail.com

Member for

19 years 5 months
Permalink

My experience ....we monitor by excel format.....but figure take it from P3.1..... update first on excel and after that convert to P3.1.....play back on remaining duration with using global change(create some formula for global change).....all tools is there..is depend user how to manage progress.....

Member for

19 years 5 months
Permalink

Hi there guys!
I work for a client organisation, we generally award Lump Sum contracts, have schedule of milestones listing CONTROL ( No LD) KEY (LD but refundable once MAJOR milestone is achieved) and MAJOR milestones ( LD non refundable)
The Contractor submits his monthly invoice based on BQ with total amount payable, this gets verified by QS & Site PMC.
I check if KEY or MAJOR milestones are late or not for the month if late then LD amount is deducted from monthly invoice.

This system is cumbersome in that EOT must be upto date ( generally its not!!)and revised milestone dates included in milestone schedule. Unfortunately, the organisation and its procedures cannot be changed.

Just thought I participate showing my frustration!!

Rgds
Dyes

Member for

20 years 6 months
Permalink

for the project i did, we define all the milestones & accumulative monthly payment ( percentage ) in the tender documents,after approved by the client,then issue to the bidders.

for some other projects our company did in Hong Kong, we let contractors define milestones & % payment during tender.
we’ll consider the future value at the completion date for the contract. that means contractors who ask less payment at the beginning have advantage to win (actually the payment do not have strong link to the quantity of work for each milestone, milestone is just a check point whether to pay or not.

I’m not sure it’s a good approach,just for your reference

Member for

24 years 8 months
Permalink

Project works are estimated before signing the contract. Thus we know the cost of works necessary to do to achieve each milestone. If milestone is achieved and approved then the predefined fixed cost is paid. This way of payment is defined by the contract. The payment milestones can be suggested by the contractor - it does not matter much. Each milestone shall represent measurable result, some object (floor, room, etc.) where some work was finished and the results accepted.
The idea - not to measure volumes because the volumes that are represented by each milestone were defined in design. If the quality is accepted and the object is approved then the cost of approved works is known.
Regards,
Vladimir

Member for

24 years 9 months
Permalink

Zhang, Vladimir:

Great. I agree. Who determines payment milestones, the contractor or the owner?
I think they should be proposed by the contractor and approved by the owner, based on specific criteria established by the owner before-hand. Which criteria would you use?

Member for

24 years 8 months
Permalink

Zhang Haixiang,
I support your approach. This way you motivate the contractors to achieving the results - not just reporting volumes and, besides, the works are not divided into more or less profitable. Both the client and the contractor have the same goals and many potential issues are avoided. We use the same approach and it works perfectly.
Best Regards,
Vladimir

Member for

20 years 6 months
Permalink

Ernesto Puyana,

One of the benefits of the milestone payment system is to avoid actual quantity caculation, the payment is based on visual achievement(milestone).

I think we can select some importane milestones as incentive/LD milestones for reward/punishment. If we load cost/resource and use earned value for schedule index, then we will lost the benefit mentioned above.

For the project I did, the total duration is around 4 years,
and we have payment milestone every 2-3 months, So we still have strong control to the project. we do not have punishment, contractor will not get the payment if the milestone is not achieved, no matter how many actual works have been done.

Member for

19 years 5 months
Permalink

More accurate ’real-time’ data can be collected by using my companies software: www.sensorynet.co.uk. We allow status to be collected from the field via wireless and mobile technologies. Please contact me for further information: malcolmg at sensorynet dot co dot uk

Member for

20 years 3 months
Permalink

Andrew,

Please allow me another question..Is there any software designed for commercial or political exercise?

thanks

Member for

24 years 9 months
Permalink

Zhang:

Do you think it would be practical to add an schedule performance index factor to milestone payments, to reward adherence to the work plan or "punish" deviations from it?

Member for

20 years 3 months
Permalink

Andrew Ng,

In which stage of the Project you consider things (in general) reasonable, equitable & fair? Can a level 1 program covers the statement? And what’s the difference between a commercial exercise & a cost control exercise?

Thank you.

Member for

20 years 6 months
Permalink

Ernesto Puyana,
I’ve also used milestone payment system for a lumpsum project.
I prepare the baseline schedule, then load cost together with commercial guys,then calculate percentage payment for each month. then prepare a milestone (most of them are on critical path) list link to percentage payment.
We put all these in the contarct. As the contractor achieved a milestone we pay the relative percentage.
during construction we never calculate actual work quantity,never argue with contractor of actual quantity, it saved a lot of time and resource.
I know the payment was not accurate, but it works well. It provie a strong control of progress, also the safety of the payment.

Member for

21 years 3 months
Permalink

Edgar,

The Simple Answer is "NO", if you can avoid it.

There is no involvement of accounting whatsoever unless we have a case of claim for "pre-tested and standard supply only” items in the project, in which case some accounting records may be necessary to justify the "earned" value.

In most construction projects, the payment on attainment of milestones for which some predetermined "earned value" have been set(as in the various stages put forward in Norzul’s post), should simply be triggered by the issuance of certain document/s like certificate of completion, or closing out of the final NCR/s or approval/passing of the final item in the ITP’s etc to signify their stage completion.

Or if interim partial payment is desired, by the measurements of a single “salient” measurement parameter like pipe lengths or cable lengths, as long as they are agreed in each case beforehand. These can be done by Site Engineers or Site Supervisors.

All these are measures designed to remove the subjectivity associated in other methods of determination of progress payment, although to call them EVMS is not strictly correct. This is really more a "commercial" exercise rather than a cost control exercise.

Nontheless, so long as they are considered reasonably equitable and fair without both having to “bust the guts” to agree on measurement(accounting ??) of the minutest of details, the purpose of the exercise has been served.

That’s what matters.

Member for

20 years 3 months
Permalink

Andrew Ng,

Are you saying that it is necessary to integrate planning with accounting in order to get the best or accurate results in taking actual percent progress?

Member for

24 years 9 months
Permalink

I’ve used the milestones payment system (100% milestones), and I think it works great, as long as partial milestones are well chosen. They should correspond to very significant activities, all part of the critical path.

That way both the contractor’s and the owner’s interests are served, since in order to get paid on time, the contractor will focus on what should be done to keep the schedule on track.

I would suggest a milestone payment combined with a reduction factor based on a schedule performance index: The contractor will be paid when the milestone is achieved, but the amount will be reduced if percent complete is below scheduled.

Member for

21 years 3 months
Permalink

Norzul,

There is no absolute right or wrong in your proposal, after all it is just simplification of the payment and measurement for the convenience of all parties involved.

If all parties can live with it, it must be alright.

After all this is strictly not any Earned Value Management(which is a cost control and project control process), but some semblance of "earned value" presumedly calculated to trigger off payment/s on progress upon reaching certain targets agreed.

Member for

19 years 10 months
Permalink

The 30% progress payment that I mentioned will be based on the actual physical progress of the installation and the agreed weightage. For example:

Agreed Weightage (based on estimated value of the proposal)
1) TOTAL PROJECT (EPCC) : 100%
2) Engineering : 10%
3) Procurement : 30%
4) Construction : 40%
5) Pre-Commissioning : 10%
6) Commissioning/Performance Test : 10%

For construction, it will be further breakdown into piping, mechanical, civil, instrument, and electrical. The weightage for each discipline will be based on estimated construction manhours.

Piping progress will be further breakdown into several system. Each system’s (for example steam piping) progress is based on achievement of the milestone i.e.
1) Pre-fab (25%) - based on actual dia-inch vs total plan
2) Erection (10%)- based on actual meter length vs total plan
3) Welding (25%) - based on actual dia-inch
4) Supports (10%) - based on numbers
5) Painting (5%) - basedon length
6) Valves installation (10%) - based on numbers
7) NDT (5%) - based on numbers
8) Pressure test (10%) - based on pressure test package

The above will be mutually agreed between client and contractor.

thanks

norzul

Member for

21 years 3 months
Permalink

Edgar

I thought the best measurement of actual "value" spent on any project should be those invoiced amounts from internal as well as external suppliers inluding those prelim items direct costs.

So far as measurement of the earned value, it has been argued that it should be on the "perceived" level of designed performance achieved(the most simplistic being 0% all the way until the machine is tested and operational i.e. 100%) which despite being representative of the "value" actually in the Clients possession when paid, may not be practical for Contractor’s cashflow position in most cases. In practices we have found all kinds of rules of intermediate assessment which have more practicallity than accuracy.

The measurement by % of physical progress is what have been encountered most in my experience if we do not wish to be compounded by "subjective" value judgement. These earned value measurements can still be as complex and tedious as any physcial BQ-type quantities measurement limited only by your desire for precision and resemblance to the physical reality.

Of the many quantities measurement, manhours is most popular being able to cut across different discipline and trades/construction elements as in the case of complex equipments or composite construction with varying degree of pre and post assembly before and after delivery.

If you so chose to have man-hours as the parameter of such measurement(as in the case you cited), you can start by determining beforehand the conversion ratio of each such machine-hour into equivalent manhours, in order to have the standard manhours as the common denominators. The value per machine hours divided by the average value of the manhour should normally be adequate representation of the contribution of each plant in terms of the value "forecast" and "earned".

Your baseline could then be calculated from the forecast manhours added to the equivalenet manhours converted from each forecast machine hours. The measurement of the progress of the "earned value" from man and plant records would then be possible, but I thought wouldnt it be accurate to call these "actual hours" rather than "earned hours" ?

Member for

19 years 10 months
Permalink

In our current project, payment is based on the combined achievement on the agreed milestones and the progress of the project. The payment for milestones constitute 70% of overall payment while the project progress is 30%. We divide this project progress payment by 10 i.e. for each 10% achievement of the progress, the contractor will get 3% payment. We have more > 10 major milestones to be monitored

Member for

24 years 9 months
Permalink

In lump sum contracts, payment is usually tied to earned value. Percent complete will vary depending on wheter earned value is measured in man-hours, dollars o other.

For example, some activities demand very little man-hours and high cost equipment. If earned value is measured in man-hours, this activity´s contribution to percent complete and therefore to payment will be smaller than it would be if the cost of the equipment determined it’s progress.

Member for

24 years 9 months
Permalink

As long as it is used only as a comparison parameter to measure performance, I think they all work the same; after all, it’s deviation one looks at. But, when payment depends on it, that’s when the discussion heats up.

Member for

20 years 3 months
Permalink

consistency between time & cost..is there any? what are the best indicators? Measuring physical progress may vary with time, costs, & units of resources. Is it proper to get the average?

Member for

24 years 9 months
Permalink

Zhang:

You are right. That’s why one should always look at both indicators side by side: percent complete and end date forecast.

A low percent complete does not necesarily mean a delay at completion, as long as critical activities are ok. and viceversa: even when percent complete is high, you can get a delay, if work is not focused on critical path activities.

Member for

20 years 6 months
Permalink

We are using CPM, so always thinking about Critical path
If not considering critical path, S-curve or other report may give a wrong picture.

e.g. you did a lot on non-critical acitvity, but delay on critical path. the s-curve may show you actual is bigger then planed ( you are ahead of schedule) but actually the project is delayed

Member for

20 years 8 months
Permalink

Ernesto,

Appreciate if you could e-mail me the sample of your report for reference. It most probably useful for me.

Shahrol Sabaruddin

Member for

24 years 9 months
Permalink

Shareef:

Hi. Each week’s update produces a projection of the project’s finish date. I plot it against time (weeks).

Same thing is done with other indicators: percent complete, productivity, concrete and steel waste, man-hours, etc.

The idea is to have different plots in the weekly report, which let management see not only the "picture" - what happened last week, but the whole "movie": what the performance has been all along the project, so they can easily spot trends and correlate the behavior of different performance indicators.

Member for

24 years 8 months
Permalink

Trends of project parameters - of finish date forecast, expected total cost and others tell more about project performance than project status information. I am glad that Ernesto has the same understanding.
But there is one more thing to control - evolution of contingency reserves. This evolution can be estimated using risk simulation and is harder to implement but most powerful.

Member for

24 years 9 months
Permalink

Great input, Clive.

Makes me realize I’m on the right track with what I’m doing. My weekly report are two pages long, containing:

Executive summary:
-work finished last week.
-work started last week.
-finish date and percent complete status, delay causes and trends.
-critical path changes and trend.
-corrective actions: results last week; suggested next week.
-prospection: work to start next week; one month lookahead.

Full color Graphs:
Percent complete S curve: scheduled vs (actual+to finish).
Summary bar chart.
Finish date evolution.
Schedule performance index.

That report goes to managment meetings. For field managers, I append a 3 to 4 page detailed printout (built using filters and layouts).

Member for

24 years 5 months
Permalink

Hi Clive,

I fully agree with what you said. But sometimes, especially when reporting to clients, contractor’s planners and execution people are not the only ones dictating what should be reported and what shouldn’t be reported. Contracts people sometimes are very demanding in this case. They would want to include some "cya" reports which may not be interesting/relevant to read/discuss now but could be very useful contractually in the future. Another reason for this is, to comply with what the contract is saying.

Just my thoughts on the topic.

Cheers,

Se

Member for

19 years 10 months
Permalink

Clive,

Fully agree with yu....that’s what happening to us now. Many reports but whether effective or not..

norzul

Member for

20 years 3 months
Permalink

Hi Rahmat,

This time I agree with you. We need inguinity in the way we monitor our schedules/project. In this way our deliverables will not be boring to our project managers.

On way of doing this is to assign a lot of colours to our reports. Attractive colours that will capture the imagination of the project team.

In addition there are software available in the market that will add three to four dimensional approach to project planning. This software will show in addition to dates the physical aspect of the project where the dates has relevance.

Cheers,

charlie

Member for

23 years 3 months
Permalink

Monitoring progress will be more interesting if we can visualize it physically. Don’t be trapped only with S-Curve, earned value, or complicated barchart.

I always use General Arrangement Drawing to plot the actual works performed and I evaluate directly the progress based on such plot drawing. Our Management also interested if we show not only s-curve or barchart but the figure of such physical progress.

Currently there is some 3D Plant View product to show progress physically but it’s too late because of late in design.

Thks

Member for

24 years 8 months
Permalink

Ernesto,
contingency reserves include cost and resources, not only time. Besides they shall be calculated and controled.
There is an interesting result of adding contingency reserves to the planned schedule - baseline schedule does not exist and Earned Value Analysis is not applicable.
Vladimir

Member for

24 years 9 months
Permalink

Vladimir:

I’ve lately included in my construction schedules activities related to acquisitions (at the beggining) and delivery (at the end), which act as buffers in the sense that on update, I check whether they become critical and if so, adjust their duration and make a warning in my weekly report to let the job manager know that available time for a certain negotiation or delivery has shrunk as a result of some particular activity or chain being delayed.

I know that`s not exactly what the critical chain people intended when they proposed buffers, but I think it works.

Ernesto Puyana

Member for

24 years 8 months
Permalink

Does anybosy work with time and cost project buffers? Project target dates and costs shall include contingency reserves (buffers). If contingency reserves remain sufficient then project performance is successful.
Earned value analysis does not work properly because baseline schedule does not include buffers. S-curves do not include buffers too.
Regards,
Vladimir

Member for

24 years 9 months
Permalink

Hello.

In my case, I perform no as staff, but an outside consultant in charge of schedule development (with staff input) and weekly monitoring and control of schedule. So I don’t get involved with cost control.

I know earned value could be tracked by hours not necesarily by dollars (pesos in my case), but I’ve found that generating S curves from percent complete calculated by Suretrak from activity durations (see Paul Harris) is quite adequate and much simpler to manage. Specially when we`re talking about 1000 to 4000 activity schedules.

If anybody wants to check my report format, I’ll gladly mail it.

Member for

19 years 7 months
Permalink

S Curves combined with start and finish dates (As-built) is the simpliest form for non-planners to under stand by far.

With regards why "Earned Value" was not mentioned I believe is because we still like to keep finances seperate to programme and possibly not reveal actual costs to others outside the senior project team.

This is my experience anyway.

Member for

20 years 3 months
Permalink

Hi All,

Then what is the best method of monitoring progress, regardless of the size of the project?

Member for

19 years 10 months
Permalink

Hi, All
And Why nobody mentioned EVA report?
In S currves we have only "Plan" and "Fact"
How about Earned Value?

Member for

24 years 9 months
Permalink

Hello.

I perform a weekly job visit to update start and finish dates as well as percent complete and remaining duration, activity by activity. upload that information to the Suretrak schedule, compute and produce several reports, using layouts and filters, which I export to a spreadsheet (Lotus, by the way, that produces much better graphics that excel).
This report includes an S curve, a summarized gantt chart and a detailed analisys of activities started, finished, pending, critical path and prospective analisys.

Might sound like a lot of work, but a well designed format makes it pretty straight forward.

Member for

19 years 10 months
Permalink

I’mcurrently involved in the cogeneration project. Almost completed the engineering. Construction just started, about 15% progress so far. We use plan vs actual S-Curves for monitoring the progress. The S Curves are based on the activities/WBS and the manpower resources. In addition to the S Curve we also use level 3 or 4 schedule to monitor the timeline.

Member for

20 years 11 months
Permalink

Critical Path Analysis is also an important monitoring tool which should be used in conjunction with ’S’ curve reporting.