the basic scheduling method is the same as commercial buildings. What you need is experience (e.g. production rate,relationships between systems...) There is so many kind of industry buildings with different size,I dont think there is template available. you need study the design first then start to prepare the schedule with your team members
Member for
22 yearsRE: Scheduling Practice for Oil/Gas or Pharmaceutical proje
Hello,
For planning, the conceptual thinking is important. For that u have to go thro complete contract documents & understand scope of work.
Some tips are as follow
a) List out the items for the project
b) Identify the durations
c) Interlink the project
Member for
20 years 6 monthsRE: Scheduling Practice for Oil/Gas or Pharmaceutical proje
Hi,
the basic scheduling method is the same as commercial buildings. What you need is experience (e.g. production rate,relationships between systems...) There is so many kind of industry buildings with different size,I dont think there is template available. you need study the design first then start to prepare the schedule with your team members