Successor

7 replies [Last post]
V Kutty
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 7 Dec 2009
Posts: 11
Groups: None
Hi,

I have a question.

We are using negative lags for example design to be finalised 60 days before Manufacture of First unit.

Manucture unit one FS(-60) Finalise design

Here the Predecessor of Finalise design is Manufacture unit one. What could I use as its successor so that Float values are good and real.

Thanks,

Vijay

Replies

V Kutty
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 7 Dec 2009
Posts: 11
Groups: None
Thanks Rodel, much appreciated.
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Thanks Rodel

I was just looking for this procedure,as I am on the way of using P6
Rodel Marasigan
User offline. Last seen 4 days 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi V Kutty,
I uploaded to snips basic steps for entering budget to P6, link below:
Basic Steps in Entering Budget
V Kutty
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 7 Dec 2009
Posts: 11
Groups: None
Thanks, any advice is welcome.

I am also keen on learning how to encorporate costs into Primavera what are the ways to do this?

Regards,

Vijay
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Vijay


In addition to Gray advice, breaking down activities as mention by Gray helps to reduce usage of high lag values and your schedule becomes more realistic.On updating it yields better solutions for foreseeing delays .
Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline
Logic should be
Finalise design FS(0) to Place Order FS(0) to Manufacture FS(0) to delivery FS(0) to Install.

There may be FAT or quality checks in there too.

If this logic gives you a delivery date significantly in advance of when you will be ready to install, you can make order, manufacture & delivery ALAP or zero float activities.
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi vijay

Try to avoid negative lags .If Finalized Design is required prior to manufacturing unit.
You can revise the link

Finalized Design {Predecessor} FS+60 days lag [If required] with Manufacture unit {Successor}