Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-01-04 18:49 Permalink As Nihat Said do not change As Nihat Said do not change any order of the columns or format of the columns you can not ADD a new resource if the resource does not already exist in the database Member for 23 years 11 months Member for 23 years 11 months Submitted by Nihat Yildirim on Mon, 2017-01-02 11:07 Permalink You might have wrong activity You might have wrong activity ID or resource IDs specified in the import file. Also don't change the order of sheets in the XLS file. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Sun, 2017-01-01 02:48 Permalink make sure that calculate make sure that calculate costs from units is set to no. if it is not run a global change and chnage it to no. Also make sure that the resource exists Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-01-04 18:49 Permalink As Nihat Said do not change As Nihat Said do not change any order of the columns or format of the columns you can not ADD a new resource if the resource does not already exist in the database
Member for 23 years 11 months Member for 23 years 11 months Submitted by Nihat Yildirim on Mon, 2017-01-02 11:07 Permalink You might have wrong activity You might have wrong activity ID or resource IDs specified in the import file. Also don't change the order of sheets in the XLS file.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Sun, 2017-01-01 02:48 Permalink make sure that calculate make sure that calculate costs from units is set to no. if it is not run a global change and chnage it to no. Also make sure that the resource exists
Member for
16 years 3 monthsAs Nihat Said do not change
As Nihat Said do not change any order of the columns or format of the columns
you can not ADD a new resource if the resource does not already exist in the database
Member for
23 years 11 monthsYou might have wrong activity
You might have wrong activity ID or resource IDs specified in the import file.
Also don't change the order of sheets in the XLS file.
Member for
16 years 3 monthsmake sure that calculate
make sure that calculate costs from units is set to no. if it is not run a global change and chnage it to no. Also make sure that the resource exists