thnxx zoltan , but i already did this and still remaining durations is changed and % complete is set to zero for some activities that was having value before importing is thre any other issue to try
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Thu, 2015-01-15 12:53
Member for
16 years 3 monthswhat is your activity type
what is your activity type and duration type on the activites that are changing
if the activity type is resource dependant then this would be why the durations are changing
also if the duration type is fixed units this could be why the durations are changing
Member for
12 years 6 monthsthnxx zoltan , but i already
thnxx zoltan , but i already did this and still remaining durations is changed and % complete is set to zero for some activities that was having value before importing is thre any other issue to try
Member for
16 years 3 monthsthe changing of actual dates
the changing of actual dates is impossible since you are only importing resource assignments
to make sure that no actual date even has a chance to be changed do not export the Activities only export the Resource & Resource assignments
then only import the resource assignments