I just tried. Its working. I can modify the relationship type.
But why it is showing only activities which already have relationships/pred & Succ in p6? There are no activities for which Pred & Succ are not assigned in p6. So if I want to assign pred & succ in excel, I have to add those activities manually in excel sheet?
Mujahid
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Wed, 2014-06-25 19:36
Thanx for suggestions. You understood my question very rightly. Grouping is what I am aleady trying.
Can you please alloborate the process how can I change relationships in excel? I know how to edit Activity names, duration etc in excel. But could not succeed in giving relationships in excel.
I will be thankfull to you.
Regards..
Mujahid
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Wed, 2014-06-25 10:22
- If you'll group it it will be easier to work group by group
- You can export into Excel, then add the links within Excel
- You'll have groups of activities which will be in a sequence. Select group by group then right mouse button then "Link activities" which wil sequence those activities.
These are only techniques. Reserve your time to create the proper logical links. This will help the project.
Hope I understood your question correctly. Good luck!
Member for
18 years 9 monthsyes mujahid
yes mujahid
Member for
11 years 4 monthsThanx Dieter..I just tried.
Thanx Dieter..
I just tried. Its working. I can modify the relationship type.
But why it is showing only activities which already have relationships/pred & Succ in p6? There are no activities for which Pred & Succ are not assigned in p6. So if I want to assign pred & succ in excel, I have to add those activities manually in excel sheet?
Mujahid
Member for
18 years 9 monthsMujahid You'll export to
Mujahid
You'll export to Excel (XLS) --> mark activities and Activity relationships --> within the map "Taskpred" you'll see the relationships.
Never modify any formatting! But you may modify the contents and add new records.
Then import this file again. Pay attention for the import configuration.
Good luck!
Dieter
Member for
11 years 4 monthsDear Dieter,Thanx for
Dear Dieter,
Thanx for suggestions. You understood my question very rightly. Grouping is what I am aleady trying.
Can you please alloborate the process how can I change relationships in excel? I know how to edit Activity names, duration etc in excel. But could not succeed in giving relationships in excel.
I will be thankfull to you.
Regards..
Mujahid
Member for
18 years 9 monthsMujahid This depends on the
Mujahid
This depends on the structure of your project.
- If you'll group it it will be easier to work group by group
- You can export into Excel, then add the links within Excel
- You'll have groups of activities which will be in a sequence. Select group by group then right mouse button then "Link activities" which wil sequence those activities.
These are only techniques. Reserve your time to create the proper logical links. This will help the project.
Hope I understood your question correctly. Good luck!
Dieter