Dear All,
I have created an EPC Schedule which consists of Eng,Proc and Cont Activities.Since this is a Turaorund Project During the construction phase the work will be done 24 hrs.
I have following settings in my project.
Project calendar is Standard.( 5 days a week and 8 hrs per day).Since this will be the working duration from Engg to proc Phase.
How ever in the construction period the working hrs should be 24 hrs per day.
so i have assigned task calendars to all the activities.
My default working hrs per day is 8 hrs from 8 am to 5 pm.
I am facing below problems.
1) the duration for the turaround act is not showing correctly. I mean in the duration tab it is showing 5 days but the start to finsh date is only 2 days.I know this is because of the working hrs per day set in the options tab.Then what is the solution for this....Can i not manage to show the dur and the start and finish dates correctly in MSP while working with diff calendar options...........
2) what should be the approach for preparing schedule involving diff working hrs in diff phases...
I dint face this problem in P6..But hrer in MSP i am clueless...
Please guide me...
Replies