Date Zone Properties-Adding project weeks

1 reply [Last post]
Dominic Planner
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

I am looking to add the project weeks to the top line in the date zone properties so that I can quickly see which weeks have elapsed. At present it is set to days. How do I amend this to weeks?

 

Thanks 

Replies

Ben Taunt
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Dominic,

Right-click on the date zone and go to Properties.  If you have project days showing already, this line will have the type set to elapsed units with the time unit set to elapsed day.  Simply change where is says elapsed day to elapsed week!

If you need to add in an extra line, change one of the unused lines to elapsed unit and elapsed week.

For further assistance, take a look at the date zone topic in the help file.

Thanks,

Ben @ Asta Powerproject