Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

User defined fields?

2 replies [Last post]
Christine P
User offline. Last seen 10 years 38 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

Hi all

I have a spreadsheet, with milestone dates on that the boss wants putting into Powerproject.  Theres several headings such as "name", "Value", Status" as well as the dates.

Im trying to make my own user defined fields for the headings.  I have created them under "User Field Manager" and selecting "bar" and "String".  Nno problem there. 

But when I add the columns onto the programme, nothing will appear in the column when I type unless I put in a token bar on the chart side.  How can I make my writing appear please?  Are there any properties I need to change.

 

Thanks

Replies

Mike Testro
User offline. Last seen 32 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Christine

The text in a user field only appears when there is a task on the gannt chart.

My advice is to keep the data on a spreadsheet amd copy paste when needed in a programme.

I will remove your surplus saves.

Best regards

Mike Testro

Christine P
User offline. Last seen 10 years 38 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

sorry for the multiple posts, my laptop was playing up