Asta Powerproject Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-09-05 18:41 Permalink Hi NathanYou have a resource Hi Nathan You have a resource set on tasks with different calendars. In the resource dialogue tick the box that says "use task calendars" and that should sort it. In the histogram graph dialogue you can also tick to spread over non working days. Hope this helps Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-09-05 18:41 Permalink Hi NathanYou have a resource Hi Nathan You have a resource set on tasks with different calendars. In the resource dialogue tick the box that says "use task calendars" and that should sort it. In the histogram graph dialogue you can also tick to spread over non working days. Hope this helps Best regards Mike Testro
Member for
19 years 10 monthsHi NathanYou have a resource
Hi Nathan
You have a resource set on tasks with different calendars.
In the resource dialogue tick the box that says "use task calendars" and that should sort it.
In the histogram graph dialogue you can also tick to spread over non working days.
Hope this helps
Best regards
Mike Testro