Senior Planning Engineer, Grupo Isolux Corsan, Energy Transmission and Distribution, Substations
Company Name : GRUPO ISOLUX CORSAN– Isolux Ingenieria S.A.
Address : P.O. BOX 22605, Doha, State of Qatar
Position : Senior Planning & Scheduling Engineer, Project Planner
Period Covered : May 29, 2010 to Present
Job Description :
- Lead the development of project controls system and tools including: Cost Control / Forecasting methods for Stewardship; Scheduling practices Progress Measurement; Other applicable processes and tools (ex. PMT Tracking / Forecasting); Support Project Management Team (PMT) with ongoing project cost and schedule analysis, reporting, forecasting, budgeting and Change Management.
- Examine and evaluate the Contractors cost and schedule control organization, plans, performance and procedures in conjunction with Project Management Team.
- Review and, where appropriate, endorse schedule, progress and cost baselines and forecast prepared by contractors.
- Analyze cost, schedule and progress trends developed by contractor in conjunction with the Project Management Team.
- Interface Management between Contractors.
- Responsible for complying with all project financial controls as set out in the Project Financial Controls Plan and the Project Control Plan.
- Responsible for identifying any issues within their span of control, planning and managing their resolution and reporting on issue resolution status.
- Identify potential project change requests and provide information and data as required by the Project for change management.
- Monitor and manage Concerto Project Management Program to ensure processes are being performed correctly, include new users and add scope modifications.
Projects Handled :
- GTC/144B/2006, Qatar Power Transmission System Expansion, Phase VIII Substations
10 Feeder / GIS Substations + 7 Substations Modification work (66/11 kV)
Customer: KAHRA MAA (Qatar General Electricity and Water Corporation)
Consultants: Package S-2-2 (Lahmeyer); Package S-4-1 (Mott Macdonald)
Company Name : KETTANEH CONSTRUCTION W.L.L. (ISO 9001:2008)
Address : P.O. BOX 22401, Doha, State of Qatar
Position : Planning & Scheduling Engineer, Project Control
Period Covered : June 15, 2007 to May 04, 2010
Job Description :
- Gathers all needed data, document and information required in planning assigned project.
- Obtain from PMT the project work breakdown structures (W.B.S.), activity durations parameters, sequence and resource allocation.
- Prepares preliminary primavera schedule based on item above.
- Optimizes and finalizes project schedule in close coordination with PMT.
- Verifies and collates daily activity/quantity tracking and resource usage and update primavera schedule.
- Releases the following reports periodically:
- Updated primavera schedule.
- Planned vs. actual productivity report.
- Man loading and equipment schedule.
- Commodity curve.
- Three weeks look ahead schedule per area of responsibility.
- Monthly and weekly narrative reports.
- Revises primavera schedule as required.
- Prepare detailed programs of isometrics to be prefabricated and erected during the week and month, according to contractor instructions for underground piping, steel structure and civil works.
Projects Handled :
- QATALUM (Qatar Aluminum)
Aluminum Smelter Plant Project (General Contractor: FATA Spa Italy)
Combined Cycle Power Plant Project (General Contractor: Doosan Heavy Industries)
Mesaieed Industrial City, State of Qatar
- Ras Laffan Olefins Company Ltd.
8458U-30Ethylene Cracker II Project
Ras Laffan Industrial City, State of Qatar
General Contractor: Technip France
- Ras Laffan Liquefied Natural Gas Co. Ltd.
RasGas Onshore Expansion, Phase II (Train 6&7 EPC) Project
Ras Laffan Industrial City, State of Qatar
General Contractor: Chiyoda - Technip Joint Venture
- Qatar Liquefied Gas Company Ltd.
Construction of five (5) LNG Storage Tank Expansion Project with a capacity of 140,000 m3
General Contractor: IHI, Ras Laffan Industrial City, State of Qatar
Company Name : TAISEI-SHIMIZU JOINT VENTURE
Address : Municipalities of Sta. Barbara-Cabatuan, Iloilo, Philippines
Position : QA / QC Engineer (Building Section)
Period Covered : April 3, 2006 to May 20, 2007
Job Description :
- Ensure that the work activity is carried out in accordance with the project specification.
- Responsible for all inspections and submittal of reports and all QA/QC documents, in accordance with the requirements of relevant approved Inspection and Test Plan (ITP).
- Assists consultants (Japan Airport Consultants) in their scheduled inspections.
- Prepare punch-list for remaining work items
- Prepare availability for inspection documents.
- Attend daily coordination meeting.
- Analyze and study project plans and specification.
- Prepare punch-list and conduct routine inspection for all finishing works prior to handover to client.
- Prepare as built documents per area, and close all remaining punch-list works and
implement corrective actions.
Project Handled : New Iloilo Airport Development Project
Client : Department of Transportation and Communication (DOTC)
Consultant : Japan Airport Consultant
Company Name : BETON BAU PHILIPPINES INC.
Supplied by ESORAJ Construction
Address : Brgy. Duyan-duyan Cabatuan, Iloilo, Philippines
Position : Site Engineer
Duration : January 24, 2005 to March 27, 2006
Job Description :
- Analyze / Study project plan and project duration.
- Prepare materials listings of all necessary items and equipment for construction.
- Inspect all installed materials if it agrees with project plan and specifications.
- Maintain daily accomplishment report.
- Prepare primavera schedule complete with resource loading, parameters and s-curves.
- Assists consultants during their scheduled inspections.
- Prepare narrative reports, updated three weeks look ahead schedule.
- Prepare forecast schedule as required.
- Maintain safety and daily housekeeping on site.
- Perform actual inventory of company properties annually.
- Prepare daily meeting report of actual activities on site.
- Manage and assign manpower schedule on respected areas.
Projects Handled :
- 990 Meters Under Ground Service Link (N.I.A.D.P.)
- 280 Meters Reinforced Concrete Box Culvert (N.I.A.D.P.)
General Contractor : Taisei – Shimizu Joint Venture
Company Name : ESORAJ CONSTRUCTION AND DESIGN SERVICES
Address : 3rd Flr. Sta. Cruz Bldg., Fuentes-Ledesma St., Iloilo City
Position : Project Engineer
Duration : April 1, 2004 to January 21, 2005
Job Description :
- Prepare sequence of work, when to mobilized and demobilized manpower and cost analysis.
- Prepare primavera schedule complete with resource loading, parameters and s-curves
- Perform estimates of materials needed for the project.
- Prepare billings of accomplishments in the project.
- Canvass material price and availability.
- Prepare building permits and other transactions regarding the project.
- Inspect all installed materials if it agrees with project plan and specification.
- Manage and assign manpower schedule on respected areas.
- Evaluate billings of all sub- contractors.
Project Handled : Ford Show Room Building, Iloilo City
Client : Ford Philippines
Company Name : ESORAJ CONSTRUCTION AND DESIGN SERVICES
Address : 3rd Flr. Sta. Cruz Bldg., Fuentes-Ledesma St., Iloilo City
Position : Quantity Surveyor / Auto Cad Operator (Part Time Job)
Duration : March 3, 2003 to March 31, 2004
Job Description : Take-off and prepare final bill of quantities, labor and material cost.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: