Planning Coordinator, ENEL - Slovak branch, Nuclear Power Plant – Mochovce – Slovakia

START Date: 
March, 2013
END Date: 
April, 2012

Coordinator Planning Engineer for civil construction, mechanical, piping and I & C for nuclear island’s contractors.

My main duty was to verify each contractor schedule and to join all this schedules in an integrated one. The scope of the integrated schedule is to see the interfaces between all contractors and to help management to take the right decision in coordination of the work inside each work area. Another duty for me is to analyze the critical paths and together with technical specialists to propose new solutions to improve the logic.

Planning Coordinator, ENEL - Slovak branch, Nuclear Power Plant – Mochovce – Slovakia

START Date: 
March, 2013
END Date: 
April, 2012

Coordinator Planning Engineer for civil construction, mechanical, piping and I & C for nuclear island’s contractors.

My main duty was to verify each contractor schedule and to join all this schedules in an integrated one. The scope of the integrated schedule is to see the interfaces between all contractors and to help management to take the right decision in coordination of the work inside each work area. Another duty for me is to analyze the critical paths and together with technical specialists to propose new solutions to improve the logic.

PLANNING COORDINATOR, Doha Asian Games Organizing Committee, Doha Asian Games 2006, Qatar

START Date: 
March, 2006
END Date: 
April, 2007

Planning Co-ordinator - DOHA ASIAN GAMES ORGANISING COMMITTEE (DAGOC), Qatar

As part of the Venues team, was responsible for planning and coordinating the Broadcast Lighting Project – Design, supply, installation, maintenance, and dismantling of fixed and portable broadcast lighting equipments in 45 games venues.  Coordinated the project from preparing the tender documents to contract closure, prepared the project schedule, monitored the progress, and reported to the management.  During the games time, addressed issues from venue teams and resolved them in co-ord

Planning Coordinator, Parsons International Limited, Tengizchevroil, Second Generation Project

START Date: 
November, 2004
END Date: 
January, 2005
  • To coordinate eight area planners and seven planning technicians ensuring that all correct project procedures were being maintained for this $2.3 billion project.
  • To ensure that all project progress databases are correctly being updated and developed as the project demands.
  • To liaise with all sub-contractors and area planners to ensure that correct progress and any assistance required in specific project areas is provided.
  • Programme reschedule for “off sites” section of the project comprising of six sub projects with 2.4 million man-hours due to engineering over

PLANNING COORDINATOR, Nikolaev shipyard Okean, Shipbuilding

START Date: 
January, 2006
END Date: 
May, 2008

 

PLANNING COORDINATOR, Novatec Solar España, PE2 - Solar Thermal Power Plant

START Date: 
October, 2010
END Date: 
September, 2011

Novatec Solar España, Murcia, Spain                                                                        Oct 2010 – Till date

http://www.novatecsol

PLANNING COORDINATOR, Saipem, CONSTRUCTION FOR KASHAGAN OIL FIELD

START Date: 
August, 2009

Current Role: Planning Coordinator

Coordinating Planning Department of Kuryk Construction Yard, Kazakhstan.

PIPE RACKS, PILES, FLARES, JACKETS, BARGES construction and Load Out at Kuryk Base, Kazakhstan (onshore) for Kashagan Oil Field (offshore)

Client:AKCO (AGIP Kazakhstan Oil Company)

L4-5 Project Schedule, using PRIMAVERA PROJECT PLANNER v 3.1

Progress monitoring and measurement

P3 schedule updating and analysis against the Base Line schedule

Critical Path analysis.