Planning Engineer, Petroserv Limited, Various projects with Qatar Petroleum and Ashghal
-Developed Projects Baseline Schedule/Execution Plans, Resources and cost loading, Manpower Histogram, Progress S-Curve, Cash Flow and Progress Measurement System. (Pre and Post Tender).
-Designed and developed Projects Progress Measurement System.
-Prepared CBS, cost control activities and cash flow analysis.
-Reviewing Sub-contractors Program Schedule/Execution Plan and integrating it into the Master baseline schedule program.
-Updating Project Schedule and Attending Weekly Progress meetings.
-Preparing Weekly and Monthly Project reports including forecasting and Look ahead, and analyzing Project’s Schedule Critical Path
-Monitoring Subcontractors work progress and auditing of work done.
-Preparation a Project's assets capitalization schedule project close out reports.
-Performing other project controls function as per contract and clients requirements.
- Company:
- Industry:
- Job Role:
- Project:
- Region: