Planning Lead, Freeport McMoran, Cerro Verde, copper mine expansion, Peru

START Date: 
July, 2014

Copper Mine expansion

Supervision of area planners.

Review & approve contractors' schedules (level IV) and "S" curves for all areas, such as conveyors, crushing, grinding, tailing thickeners and dam, Rail terminal, power distribution, infrastructure, WWTP, and pipelines.

Detailed review and critical path analysis of recovery plans with regard to resource loading, feasibility and interfaces with otheres.