Internal Change Order

Hello Everyone,

Just a topic on Change Order but Internal. Say a situation like, 

"Its a Engineering Project. The Client has given the Scope of Work and the Contractor has prepared a deliverable list. But at one time Contractor came to know that this deliverables are not enough as per the scope of work. So we need to prepare more deliverables. So internally the Project Manager asks the perticular dicipline engineer to prepare those extra deliverable which was not accounted in the Original Deliverable List." This Change cannot be issued as a change order to Client as it was already in the original scope.

So how would you manage such a Change. Has someone managed such a Internal Change.

 

Regards

Jithin

Z
Zoltan Palffy 👤 Member for 17 years

yes you can set it up to self populate then you cna set it up to import the activities into p6 from excel 

notice it tied it to existing activities on the bakc end and well as kicking off the change order with a constraint date this actviivity should also tie to the begining of the project becasue every activity must have a predecessor and a successor 

J
Jithin Kambhikanam 👤 Member for 15 years 4 months

Got it Zoltan. Thanks. Really a good one indeed. Gives a good Idea with a Situation.

 

Thanks Again.

 

Regards

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 4 months

Thanks Zoltan,

 

The schedule part got it. What about presenting it in Excel. Example

Category Deliverables Budget Hours - A ICO - B Total Budgeted Hours - C = (A+B) Change Order - D Total Budgeted -E = C + D
CTR PFD 80   80   80
ICO Flare Dispersion Study   40 40   40

So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.

Regards

Jithin

 

J
Jithin Kambhikanam 👤 Member for 15 years 4 months

Thanks Zoltan,

 

The schedule part got it. What about presenting it in Excel. Example

Category Deliverables Budget Hours - A ICO - B Total Budgeted Hours - C = (A+B) Change Order - D Total Budgeted -E = C + D
CTR PFD 80   80   80
ICO Flare Dispersion Study   40 40   40

So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.

Regards

Jithin

 

Z
Zoltan Palffy 👤 Member for 17 years

Many ways to do this. Add the activities in and creat a code called ICO internal change order and tag all of the added activities with this code. Do not add any cost assoicated with this change if yo uneed to track then track it in a spreadsheet and out these cost below the line this wil come of of your profit for the project or if you have any contingency.

Featured Partner

Top Posters

Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts