Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

contract dispute

1 reply [Last post]
ronron martinez
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear All

In the tender document drawing few items only mention however in the Issue for construction drawing have mention few items but not indicated in the scope of works under the contract clause, Is it a variation order, please advise.

Regards,

Ronron
 

Replies

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronron

It all depends on the type of contract.

If you have a remeasurable BOQ then you get paid for the work you do the number of drawings is variable as the work progresses.

Anything else - such as fixed price - EPC - then you have a big problem without a clearly defined scopeof work.

Best regards

Mike Testro