Templates for Highway Projects

M
madhu kumar 👤 Member for 10 years

Helo Everyone ,

Can someone help me how to implement "line of Balance" method in a highway project .

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear MD,



Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs.



The activities, sequence, resources, and duration, can be determined with the construction crews at site.



But in general, you will have the followign divisions:

I. Roads

a. Excavation and Fill

b. Subbase

c. Basecourse

d. Asphates

II. Structures; buildings, bridges, culverts.

a. Substructures

b. Superstructures

III. Electrical

IV. Mechanical

V. Signage



If you have a more detailed question, please let us know.



With kind regards,



Samer

Forum Sponsor

Top Posters

Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts
Moahmed
0 posts