Templates for Highway Projects

M
madhu kumar 👤 Member for 10 years

Helo Everyone ,

Can someone help me how to implement "line of Balance" method in a highway project .

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear MD,



Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs.



The activities, sequence, resources, and duration, can be determined with the construction crews at site.



But in general, you will have the followign divisions:

I. Roads

a. Excavation and Fill

b. Subbase

c. Basecourse

d. Asphates

II. Structures; buildings, bridges, culverts.

a. Substructures

b. Superstructures

III. Electrical

IV. Mechanical

V. Signage



If you have a more detailed question, please let us know.



With kind regards,



Samer

Featured Partner

Top Posters

Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts
Manjeet Yadav
0 posts
Pan
0 posts