Labour calculation

8 replies [Last post]
James Thorpe
User offline. Last seen 16 years 33 weeks ago. Offline
Joined: 4 Sep 2005
Posts: 15
Groups: None

Dear Planners

Please help me to calculate the labours/gang for following activities:

a) 75 mm thick Screed

Duration available = 4 weeks, Quantity =2116 m2

How many labours/Gangs are required to finish this job in 4 weeks?

b) 20mm thick Render over blockwork. Skim over render board

Duration available = 3 weeks, Quantity =2116 m2

How many labours/Gangs are required to complete this job in 3 weeks?

c) Flooring

5mm thick carpet tiles= 1253 m2

How many labours/Gangs are required to finish this job in 3 weeks?

5mm approx for vinyl tiles = 754 m2

How many labours/Gangs are required to finish this job in 3 weeks?

5mm approx for Matting = 109 m2

How many labours/Gangs are required to finish this job in 3 weeks?


Thanks

James

Replies

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Shaik

It is a good idea to check the original date of a thread before taking time to prepare a detailed answer.

It may not be appreciated 4 years later.

Best regards

Mike Testro

shaik yakub
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 12

Nornally it is 60Mhrs - 85 Mhrs with an AVG of - 75 Mhrs/Ton However depends upon the type of work (Raft,Wall,Column,Slab)& dia of rebar.

 

Regards,

Shaik

Mahantesh Barikar
User offline. Last seen 13 years 42 weeks ago. Offline
Joined: 31 Jan 2011
Posts: 2
Groups: None

Can any one tell how many labour required for 01 metricton of reinforcement work.

Rubas M. Kutty
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 21
Groups: None
Assumed a 5-day week for the inputs
The production rates:

75 mm screed : 3 sqm/hr
Render : 3 sqm/hr
Carpet tile : 3 sqm/hr
Vinyl sheet : 5 sqm/hr.

PS: There was a miscalculation w.r.t Vinyl sheetings.

Regards,

Nar Thap
User offline. Last seen 16 years 29 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 73
Can somebody of you who answered pls. also post the basis for coming to that result ? Helpful for members. rgds,
Kieran Thomson
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 28 Jan 2004
Posts: 43
Groups: None
For the screed get it mechanicaly pumped and laid, should take a week and remember it needs to go off before you work on it whatever way its thrown in, and dry before you lay anything on it (that could take up to 7 weeks).
James Thorpe
User offline. Last seen 16 years 33 weeks ago. Offline
Joined: 4 Sep 2005
Posts: 15
Groups: None
Thanks kutty for you help.

Other members comments would also be appreciated.
Rubas M. Kutty
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 21
Groups: None
Hi James,

These are the rough figures.

A) 4.5 nos
B) 6 nos
C) Carpet tiles - 3.5 nos
Vinyl sheets - 6.3 nos
I am not having data for the matting. Trust this helps.

Regards,