P6 export for Budgeted Units Early & Late by month for S-Curves in Excel

7 replies [Last post]
Nicolas Berger
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 12 Jun 2006
Posts: 46

Hi to All,

I am trying to do on P6 (V7) what I used to do when I was working on P3 a several years ago.

I used to generate my S-Curves on Excel from P3 by computing a Tabular Report displayed the following way :

TimeEarly startLate StartEarly FinishLate Finish
Month 1Budgeted UnitsBudgeted UnitsBudgeted UnitsBudgeted Units
Month 2Budgeted UnitsBudgeted UnitsBudgeted UnitsBudgeted Units

It was extremely useful and very easy to generate Early & Late Curves as well as forecast curves.

What I see today from P6, is only a way to export to Excel, the distribution budgeted units on a singular date but not Early and Late dates

 

How can I do that ?

 

Thanks very much in advance Planning Community

 

NB

Replies

Nicolas Berger
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 12 Jun 2006
Posts: 46

That's it great thanks !

Berker Colakoglu
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 11 Jan 2008
Posts: 13
Groups: None

You can not copy and paste from resource usage spreadsheet ,try from Project/Resource assignments .

Nicolas Berger
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 12 Jun 2006
Posts: 46

I go back to this topic since indeed I finally succeeded to display on P6 the right columns and Rows but I can't make any copy/paste into Excel then.

Does anyone have an idea how to copy/paste those kind of values in the 'Resource Usage Spreadsheet' or 'Activity Usage Spreadsheet' ?

 

Thanks,

NB

Mark Anthony Amores
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 17 Nov 2012
Posts: 4
Groups: None

Hi all,

I have some problems with deriving reports on cash flow. I cant run tabulated reports on cash flow showing

early and late cost. I have modified on the Reports Editor but still it doesnt work out.

Can anyone please help me how to extract those reports? I am using Primavera P6 version.

 

 

Thanks,

Mark

Mark Anthony Amores
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 17 Nov 2012
Posts: 4
Groups: None

f

Nicolas Berger
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 12 Jun 2006
Posts: 46

That's great thanks so much.

 

very helpful !

Berker Colakoglu
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 11 Jan 2008
Posts: 13
Groups: None

Hi,

On the assignments page , at the distribution side, you can click display then go spreedshield fields then customize and you can find remaining early and late units under time interval/units and you can add them to your distribution layout.

So the distribution rows will be early and late units.

Regards,

Berker