Baselined dates change when assigned back to the plan

I have amended some activities on the restored baseline and the dates are all accurate.  When I then assign the baseline back to the main plan a couple of the baseline dates change back/ close to the data date.  This only happens to a couple of activities. Any ideas?

Also I have tried adding new activities to the restored Baseline plan but when it is assigned to the main plan the activity is not present?  I have checked all filter etc but cannot see a reason why.

Any help on either of these would be great.

 

Regards

Nath

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts