P6 - (Activity % Complete) is not getting summarized as compare to other columns.

5 replies [Last post]
Ameen Pasha
User offline. Last seen 10 years 27 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 21

Dear Expertise of P6.

With reference to above mentioned subject i.e. P6 - (Activity % Complete) is not getting summarized as compare to other columns. your valuable inputs are required.

Awaiting your usual positive feedback, please consider the snap shot attached herewith for easy refence.

Thanks in advance.

 

1021
activity.jpg

. Awaiting  

Replies

Mohd Nizam
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 19 Apr 2005
Posts: 16

Ameen,

you need to configure your performance % complete either you want it to be base on Duration % complete, unit % complete and only performance % complete will show a summary / roll up figures

Deepak Jain
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 27 May 2011
Posts: 13
Groups: None

Ameen,

Suppose, on a project if Design is 20% , Procurement is 10% and Construction is 5%, Would you expect P6 to show you summary % as 35% ? So, There's this logic why P6 doesn't show Activity % at summary level.

To get overall %, you need to define a common variable among multidisciplinary project activities

Cheers,

Ameen Pasha
User offline. Last seen 10 years 27 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 21

It is Man Hours loaded and the desired results are coming via Global Change application.

Erik Lange
User offline. Last seen 12 years 4 days ago. Offline
Joined: 6 Oct 2011
Posts: 4
Groups: None

That particular column does not appear to summarize since it is called "Activity % Complete" as opposed to "% complete".

If you want the summary you have to choose the percent complete type that you are using (based on duration, cost etc.). So if you are using durations, you need to select the "Duration % Complete" column and that will summarize based on your durations.

Ferdinand U.
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142

Hi Ameen

Activity % summary can be found on the selected percent complete type you assigned for the project (Duration %, Units %), physical % is a different story

If it is cost loaded, check the performance % and cost % or expense %

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3

.