Hi,

I developed one programme with labour units input (resource). While preparing the resource distribution month wise, it was working smoothly from Toools- Report Wizard. But not working properly with Resource spread sheet.

Problem in detail:

1. From Tools- Report wizard, I ticked the box for average and put the value as 30(to divide) to get a monthwise average

2. When I tried the same using the Resource Using profile and put the value as 30 its still showing the cumulative only.

For eg: 30 man days in a month. as average 1 person (Tools-Report wizard calculation)

same showing as 30 with repource profile  (even with the average box ticked and value as 30)

Any ideas what may be wrong. I presume some tick box missing.

Regards

Kannan

 

 

Featured Partner

Top Posters

James Williams
75 posts
Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners