Resource Usage Profile

No replies
Kannan CP
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi,

I developed one programme with labour units input (resource). While preparing the resource distribution month wise, it was working smoothly from Toools- Report Wizard. But not working properly with Resource spread sheet.

Problem in detail:

1. From Tools- Report wizard, I ticked the box for average and put the value as 30(to divide) to get a monthwise average

2. When I tried the same using the Resource Using profile and put the value as 30 its still showing the cumulative only.

For eg: 30 man days in a month. as average 1 person (Tools-Report wizard calculation)

same showing as 30 with repource profile  (even with the average box ticked and value as 30)

Any ideas what may be wrong. I presume some tick box missing.

Regards

Kannan