Wrong Summary Percent Complete

I have a situation within same project. Some WBS summaries are calculating duration percent complete correctly, while other WBS summaries are showing ZERO duration percent complete with activities having actual pecent completes. Pls, any ideas why and means to correct it.

Thanks