P6 Calculation fixed unit/Time

5 replies [Last post]
walid Lahiani
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

GOood morning ,

This is the question

I changed the data date and pressed F9 =>the remaining duration didn't changed but at complete duration increased

I want that remaining duration change automatically so the remaining units in ressources increase and the formula


AT COMPLETE DURATION =Actual duration+Remaining duration still correct

thanks

Replies

Ravikumar Allada
User offline. Last seen 12 years 20 weeks ago. Offline
Joined: 29 Mar 2012
Posts: 2
Groups: None

I would like to know how to copy the budgeted  units activity wise on a weekly timescale in P6

Somasundaram K
User offline. Last seen 11 years 5 days ago. Offline
Joined: 22 Nov 2010
Posts: 5
Groups: None

Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

Please let me know if this is not what you meant. Thanks!

Somasundaram K
User offline. Last seen 11 years 5 days ago. Offline
Joined: 22 Nov 2010
Posts: 5
Groups: None

Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

Please let me know if this is not what you meant. Thanks!

Frederic Fasquelle
User offline. Last seen 1 year 26 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Hi Somasundaram K,

I jump of your proposal and I would be interested to get any feedback.
To update my project, I am filling "Expected Finish" field (only activity started).

First consequence is to get FF=0 on this activty.

Is there any other consequence in scheduling ?
Is it a good practice to fill this field instead of modifying directly finish date ?


regards

Somasundaram K
User offline. Last seen 11 years 5 days ago. Offline
Joined: 22 Nov 2010
Posts: 5
Groups: None

Schedule using Expected Finish date field. That should solve your problem. Thanks!