Recurring activity in P6

1 reply [Last post]
Sarah Sargeant
User offline. Last seen 6 years 28 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 13

Hi all,

 

I need to put a recurring activity in a schedule to show a meeting which is scheduled every 6 weeks. Is this possible in P6, if so, can anyone tell me how to do it please?

 

Many thanks.

Replies

Mike Testro
User offline. Last seen 28 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jane

Set up a calendar that has one work day in a six week period of non work days and apply it to your "Meeting" task - the duration should be the number of anticipated meetings.

Make sure you add progress to block out the meetings as and when they occur.

Best regards

Mike Testro