Automatic changing of the Data Date in PM6

3 replies [Last post]
Eric Rivera
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 2 Jul 2008
Posts: 9
Groups: None

Hello all!

So I'm having an 'issue' that I have never seen before. I recently imported a project over from MS Project into PM6 (something I've done on several occasions).

But this time, it carried with it a setting that seems to automatically be making the DATA DATE the CURRENT DATE.

I've never used, needed, or even seen this before, so I'm not sure where this setting resides in PM6 so that I can TURN IT OFF!

Can anyone direct me to the right menu so that I can shut that down?

Thanks in Advance,

Eric

Replies

Russell Manuba
User offline. Last seen 11 years 9 weeks ago. Offline
Joined: 5 May 2013
Posts: 16
Groups: None

Hi Eric,

 

I'm also encountering your problem which is really frustrating coz after i plotted dates to all activities and press F9 they get back to their previous dates or to the data date. I checked out the the check box mentioned by Rajesh but same as you, the check box is currently unchecked and is uncheckable. 

I aslo imported this file from MS project. Could this be something with the MS project? 

 

Russell

 

kumar s
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Eric,

Good Info

I want to use this setting of 'Set Data Date and Planned Start Date to Project Forecast Start Date during Scheduling'.

But the option now is unchecked and it is not possible to check it.

so where can i change it.

 

Rgds

Rajesh Khanna Sake
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 14 Sep 2006
Posts: 14
Groups: None

Eric,

Under Tools/ Schedule, there is a check box - 'Set Data Date and Planned Start Date to Project Forecast Start Date during Scheduling'. Make sure that it is unchecked. I can only think of this option.

Let me know if it works.

Thanks,

Rajesh