Please i need help with a proficient p6 user !!!!!!!!!!!!!!!! HELPPPPPPPPPPPPPPPPPPPP HeLPPPPPP

B
BRAVE G 👤 Member for 15 years 8 months

Just want to validate this with youuuuu. I am confined to primavera p6 so there's no alternative. please advice if you have recently used primvera p6 or very conversant with p6

 

1. You plan in p6  lets say PLanA

2. Now you update by selecting project, maintain baseline, then copy. this will save a copy of your original plan.......

3. You select project Assign baselines and make this your project baseline and primary baselines.....

4. Then you update your plan with the actuals and so onnnn.

Now you want to replan so you UNLINK your baseline from your PlanA then you replan..... PLan A <R> 

 

My question is if you want to unpdate the second time or after you have amended your plan wat will make ur baseline.........

please HeLPPPPPPPPPPPPPPPPPPPPPPPPp

Featured Partner

Top Posters

Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts