number of activities

4 replies [Last post]
M. Kamel Bessekri
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 27
Groups: None

Hi all

are there  tips to get the number of the total activities and also per wbs level ?

thanks

Replies

Mathieu ALBOUY
User offline. Last seen 13 years 11 weeks ago. Offline
Joined: 20 May 2011
Posts: 8
Groups: None

Activity Count in a column easy reachable (View Menu/Column/customize/ Available option).

It works well and its availbale in Project, WBS, Activities view (the most usefull ones)

Seyyit Eren Paydak
User offline. Last seen 11 years 41 weeks ago. Offline
Joined: 30 May 2011
Posts: 4

Hi all,

Or you can try "activity count" column..

Regards..

Eren Paydak

M. Kamel Bessekri
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 27
Groups: None

Kumar

thank you very much

kumar s
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

kamel

you can find it in the WBS layout .

select total activities in the columns.

cheers