Resource report for day by day

Dear All,

For my project, we want to know, how many no of columns we would be casting daily. to solve this i created a resource named as Columns and assigned it to the activity. I counted the no of columns on each floor and then assigned the nos to the activity. now can anybody tell me how to get this printed on daily basis for entire project. P6 gives for monthly basis but i want it for daily.

M
Mangesh Khuspe 👤 Member for 19 years 2 months

Dear Anoon,

 

There is some confusion going on ( I suppose). I have counted the No of Columns from the drawing and added this as a resource to Column activity in the program. Now the Program gives resource usage for the duration of activity. i want to know the no of columns which are to be cast on daily basis. which i have tried through the Report editor, but failed to do so.

I hope i am clear now.

A
Anoon Iimos 👤 Member for 19 years 8 months

If you are working on a high rise building, the columns will be dependent on the casting of the floors, why don't you just count directly from the drawings?

M
Mangesh Khuspe 👤 Member for 19 years 2 months

Dear Anoon,

Thanks for the reply, I didnt understand what you want to say. can you please explain?.

This is the simplest method for me as it will give the daily usage of resource.

 

 

 

 

 

A
Anoon Iimos 👤 Member for 19 years 8 months

you can make your timescale on a daily basis, but I supposed your approach is wrong, it will depend on how you structure your activities

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts