change a resource assignment

J
Johnny Pain 👤 Member for 20 years 10 months

hi all,

 

you know, in the resource assignment view, when you change a resource for another ?

P6 asks if you want to reset the remaining units/time (or something like that) for the new resource ?

 

a colleague of mine accidentally checked the box hiding this question for the future AND the wrong answer, so each time he changes a resource for another, it resets the upt with the default value set for the new resource.

 

where can we find the option in P6 to put it backwards ?

or can we make P6 ask again for each change ?

 

I tried different settings in the project/resources and project/calcultations tabs but I can't find it...

 

thank you !

 

 

djo

F
Ferdinand U. 👤 Member for 19 years

edit menu, user preferences, under calculations tab, Assignment Staffing, check the option "ask me to select each time i assign"

Featured Partner

Top Posters

Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts