change a resource assignment

3 replies [Last post]
Johnny Pain
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 23 Sep 2005
Posts: 47

hi all,

 

you know, in the resource assignment view, when you change a resource for another ?

P6 asks if you want to reset the remaining units/time (or something like that) for the new resource ?

 

a colleague of mine accidentally checked the box hiding this question for the future AND the wrong answer, so each time he changes a resource for another, it resets the upt with the default value set for the new resource.

 

where can we find the option in P6 to put it backwards ?

or can we make P6 ask again for each change ?

 

I tried different settings in the project/resources and project/calcultations tabs but I can't find it...

 

thank you !

 

 

djo

Replies

Johnny Pain
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 23 Sep 2005
Posts: 47

thanks a lot !

it works fine !

Jia Qian
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 14 Dec 2010
Posts: 5
Groups: None

excellent answer............

Ferdinand U.
User offline. Last seen 7 years 2 days ago. Offline
Joined: 19 Jul 2007
Posts: 142

edit menu, user preferences, under calculations tab, Assignment Staffing, check the option "ask me to select each time i assign"