Confusion in Negative Lag

5 replies [Last post]
Irfan Khan
User offline. Last seen 13 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all,

 

I am scheduling for infrastructure project. I startd my Project from 01-07-2010 and finish date is 12-01-2011.

i linked each & every activities but i m unable to define critical path. at last my lag is coming (-1).

even i m finishing my project on 12-01-2011.

i dont know how is coming i am facing this problem 1st time.

pls give me any solution ..

 

thanks.....

Replies

niles luo
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None

hi,

   I think the reason is the same with "Maybe the “must finish” date is set up for early in the morning while projected finish is for the same date late in the evening."

  Pls confirm it by showing the hours of date.

Best Regards. 

Irfan Khan
User offline. Last seen 13 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

thanks for reply,

 

but i m changing date of must finish it is still showing minus lag (-1).

 

hv any other solution..

thanks.......

Rafael Davila
User offline. Last seen 1 hour 59 min ago. Offline
Joined: 1 Mar 2004
Posts: 5233

Maybe the “must finish” date is set up for early in the morning while projected finish is for the same date late in the evening.

walid Lahiani
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

hello

Dont worry khan,

you have to change the must finish date of the project

that's why I think the total float =-1

walid Lahiani
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

hello

Dont worry khan,

you have to change the must finish date of the project

that's why I think the total float =-1