Start and Finish FLOAT

A
Ali Farhat 👤 Member for 17 years 8 months
V
Vladimir Liberzon 👤 Member for 25 years 5 months

Start Float shows the delay of sctivity start that does not delay project finish if everything will be done as expected.

Finish float shows the delay of activity finish that does not delay project finish if everything will be done as expected.



Actually it is more interesting to understand the delay of activity finish that will not delay project finish if current activity will be done slower than expected (we call it super float).



I think that start float is most useful because you decide when to start each activity. When start is known finish is defined.

A
Ali Farhat 👤 Member for 17 years 8 months

So what is the use of the option in Scheduling dialog box that allows you to choose betwee start float, finish float, or the smallest between them?

R
Rodel Marasigan 👤 Member for 19 years 8 months

Ali,

One is calculated by Forward Pass and the other is calculated using Backward Pass.

S
Shah. HB 👤 Member for 17 years 7 months

Hi Ali



Both yields same result but the way of computing is different

Featured Partner

Top Posters

yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts

Our Partners