Dear Rodel,
When i keep Must Finish by date of my project by 24th July 2011 time 7:00pm , Primavera is showing my completion date of my project as 25th July 2011 with Zero total float?? How is it possible....
I have used a Level of effort activity called Project Duration. Project duration activity" is linked to start-start with "first activity of the Project i.e. Project start date and finish to finish with last activity of the project i.e. Project Finish date....it is showing the entire Project Duration..Now this level of effort activity is showing completion as 25th July 2010 10:00 am....
And also if i change my Must finish date time to 24th July 2011 , 1:00 pm , then Primavera now shows project finish date as 24th July 2011....
So kindly explain me why primavera takes project completion as 25th July 2011 , when i set my Must finish by date as 24th July 2011 , 7:00 pm.
regards,
Haresh