The post was already more than ten years ago, but no solution was posted.
I encountered the same problem, wherein the At Completion keeps changing whenever I calculated the schedule after I update the actual units.
I discovered the solution from Rodel's post. The straightforward solution is to:
Go to Project Window>Calculations Tab>Resource Assignments. Then uncheck the condition [Recalculate Actual Units and Cost when Duration % complete changes. And Voila, the problem is solved.
I speculate that 10years ago, this option is not yet available in the previous version of P6. My P6 version using now is Primavera Release 8.3.0
Its been 10 years, but i still want to reply on this post to improve my knowledge.
I encountered Similar problem as the above wherein whenever i update my Programs my Resource Assignment Changes.
My work around in this is to Check my BL loading and compare with the Updated Program to correct the Budgeted Units.
After that since my Reporting system is based on At Completion units. I also have to correct the At Completion Units.
What happens is that whenever i actualize activities, the Actual, Remaining and At Completion is displaying zero which gives me wrong data. Therefore, (for my solution) i use below steps in the Updated Program after i export:
1. Budgeted Units = At Completion units
2. Actual Units = At Completion - Remaining Units.
I hope to understand why this happens in the Primavera Program. Hope you can give Advice.
First change the setting on Project Windows-> Calculation Tab-> Resource Assignments. Make sure Subtract Actual from At Completion is selected or tick.
Remaining Labor Unit = Budgeted Labor Unit - Actual Labor Units
Do the same on all Resource Type use or assign on current Projects.
Alternatively export Resource Assignment to excel spreadsheet with the following Fields: Activity ID, Activity Status, Resource ID, Roles ID, Account ID, Budgeted Units, Actual Units, Remaining Units and At Completion Units.
Update Remaining Units = Budgeted Units - Actual Units and At Completion Unit = Actual Units + Remaining Units
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Mr. Rodel,
Its been 10 years, but i still want to reply on this post to improve my knowledge.
I encountered Similar problem as the above wherein whenever i update my Programs my Resource Assignment Changes.
My work around in this is to Check my BL loading and compare with the Updated Program to correct the Budgeted Units.
After that since my Reporting system is based on At Completion units. I also have to correct the At Completion Units.
What happens is that whenever i actualize activities, the Actual, Remaining and At Completion is displaying zero which gives me wrong data. Therefore, (for my solution) i use below steps in the Updated Program after i export:
1. Budgeted Units = At Completion units
2. Actual Units = At Completion - Remaining Units.
I hope to understand why this happens in the Primavera Program. Hope you can give Advice.
Thanks,
Hi
Thx
Its working perfectly
Izam,
First change the setting on Project Windows-> Calculation Tab-> Resource Assignments. Make sure Subtract Actual from At Completion is selected or tick.
Then run Global Change
Select Subject Area: Activity Resource Assignments
If
Resource Type equals Labor
Then
Remaining Labor Unit = Budgeted Labor Unit - Actual Labor Units
Do the same on all Resource Type use or assign on current Projects.
Alternatively export Resource Assignment to excel spreadsheet with the following Fields: Activity ID, Activity Status, Resource ID, Roles ID, Account ID, Budgeted Units, Actual Units, Remaining Units and At Completion Units.
Update Remaining Units = Budgeted Units - Actual Units and At Completion Unit = Actual Units + Remaining Units
Then import it back.