Two different sets of calendar

4 replies [Last post]
albi hijir
User offline. Last seen 6 years 52 weeks ago. Offline
Joined: 24 Mar 2010
Posts: 4
Groups: GPC Qatar
Hi Everyone

It is possible to use two different sets of calendar in a single project?







many thanks

Albi

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Albi,

Click link below. I explained the proper use of multiple calendars
Multiple Calendar Scheduling Post #3
albi hijir
User offline. Last seen 6 years 52 weeks ago. Offline
Joined: 24 Mar 2010
Posts: 4
Groups: GPC Qatar
Rodel,


If (i.e 6/days 8 hrs/day is my default calendar) and the other
calendar is 6/days 6 hrs/day if I`m going to assign it to one of my activity? what step should i do? some hint would be a big help.

Thanks in advance sir

best regard
albi
Irfan Khan
User offline. Last seen 13 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
Hi,

yes u can assign more than 1 calender for 1 Project.

R
Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Albi,
You can use multiple calendar in one single project.