you do not edit the resource spreadsheet the costs and units are spread over the activities start and end date based on the cost and units that you input for the resource.
this is based on your calendar and availabe work hours per day.
the only way to change distribution is to change the duration, chnage the costs, change the units or assign a curve to the resource so that the distribution is different.
In a project I need to distribute fixed cost across the task duration manually without resource. I was trying to enter cost in Cost usage sheet. But found this is not editable. Like Activity No 2 August-2014 Plan cost is $15,000 and September-14 is $ 16,500. How can I edit this numbers.
As mentioned in previous post, you cannot edit/modify cost manually whether it is Labor, Nonlabor & Material Resource Type.
This is just a suggestion, I think the best thing you can do is to set your Budgeted Cost equal to your Budgeted Units. To perform this try the following:
1. I pressumed you have cost-loaded schedule and no Budgeted Units in your schedule.
2. Perform a global change or do it in Excel.
Select Subject Area = "Activity Resource Assignments"
Where
Resource ID Name "is under" "Assigned Resource ID/Name"
Then
Budgeted Labor Units = Budgeted Cost
3. When done, set your Price/Unit = 1
4. Do not forget to "Recalculate Assignment Cost" under Tools Menu.
Now, You have a Budgeted Unit & Cost. If you wish to modify your Budgetd Units, your cost as well will be modified and updated according to your units.
If you find some difficulties try to send PM to me.
It maybe using roles instead of resource and you also needs privileges to edit roles assignment for planning under Security Profile-> Project Profiles.
Note: You can only edit budget units and remaining units and not cost fields.
I have the duration type Fixed duration & units and I also have security priviliges to edit resource assignments. Also I checked the possible cause that are metioned in the help menu of PM, but to no vail.
Probably, some one else can guide me if there is some secret behind it.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
you do not edit the resource spreadsheet the costs and units are spread over the activities start and end date based on the cost and units that you input for the resource.
this is based on your calendar and availabe work hours per day.
the only way to change distribution is to change the duration, chnage the costs, change the units or assign a curve to the resource so that the distribution is different.
this is not excel
In a project I need to distribute fixed cost across the task duration manually without resource. I was trying to enter cost in Cost usage sheet. But found this is not editable. Like Activity No 2 August-2014 Plan cost is $15,000 and September-14 is $ 16,500. How can I edit this numbers.
Thanks.
Hi Ijaz,
As mentioned in previous post, you cannot edit/modify cost manually whether it is Labor, Nonlabor & Material Resource Type.
This is just a suggestion, I think the best thing you can do is to set your Budgeted Cost equal to your Budgeted Units. To perform this try the following:
1. I pressumed you have cost-loaded schedule and no Budgeted Units in your schedule.
2. Perform a global change or do it in Excel.
Select Subject Area = "Activity Resource Assignments"
Where
Resource ID Name "is under" "Assigned Resource ID/Name"
Then
Budgeted Labor Units = Budgeted Cost
3. When done, set your Price/Unit = 1
4. Do not forget to "Recalculate Assignment Cost" under Tools Menu.
Now, You have a Budgeted Unit & Cost. If you wish to modify your Budgetd Units, your cost as well will be modified and updated according to your units.
If you find some difficulties try to send PM to me.
Regards,
Arnold
Thank you Arnold,
What about if we have Non-labor cost like miscellaneous cost charges or material cost. How can we spread this cost manually.
Hi Ijaz,
I agree with Rodel, you cannot modify/edit cost but only budget units and remaining units.
Tell us what is really your intention otherwise, we can suggest another perspective.
Regards,
Arnold
Ijaz,
It maybe using roles instead of resource and you also needs privileges to edit roles assignment for planning under Security Profile-> Project Profiles.
Note: You can only edit budget units and remaining units and not cost fields.
Hi Rodel,
I have the duration type Fixed duration & units and I also have security priviliges to edit resource assignments. Also I checked the possible cause that are metioned in the help menu of PM, but to no vail.
Probably, some one else can guide me if there is some secret behind it.
Thanks
Ijaz
Ijas,
You cannot edit cost only remaining units and budgets units.
Another cause is duration type settings: Fixed Units and Fixed Unit/Time are not editable in spreadsheet.
Worse scenario: You dont have privilege to edit resource assignment for Planning under Security Profile-> Project Profiles