Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Estimate to Complete Calculation

1 reply [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi Guys,
Can anybody tell me which CPI the P5 is using while caculating Estimate to Complete in the formula:

ETC = PF * (Budgeted - Earned)

I have set PF = 1/Cost Performance index

Thanks
Ijaz

Replies

K D
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi.
If I’m not wrong there is only 1 CPI.
CPI = Earned value / Actual cost.