Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating activity dates, %complete

2 replies [Last post]
ladi sodipo
User offline. Last seen 8 years 30 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 27
I am tryng to change my activity dates cus the activities were completed earlear, but i can’t seem to get my % complete to change. what might be the problem?

Replies

Patricia Le Clainche
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Johny is right, regarding Schedule Update.
I would add, that the Activity % complete (technical progress) will depend on the EVT you choose in WBS view.

Regards.


Johny Kesserwany
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Your question is not very clear! What do you mean by “I am trying to change my activity dates ..” Are you doing an update? If this is the case you have to check :
•The actual start
•The actual finish
•The remaining duration for activities started and not finished
•The data date
•The schedule function (F9)

Regards