Updating activity dates, %complete

L
ladi sodipo 👤 Member for 18 years 8 months
P
Patricia Le Clainche 👤 Member for 19 years 2 months

Johny is right, regarding Schedule Update.

I would add, that the Activity % complete (technical progress) will depend on the EVT you choose in WBS view.



Regards.




J
Johny Kesserwany 👤 Member for 18 years 9 months

Your question is not very clear! What do you mean by “I am trying to change my activity dates ..” Are you doing an update? If this is the case you have to check :

•The actual start

•The actual finish

•The remaining duration for activities started and not finished

•The data date

•The schedule function (F9)



Regards

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts

Our Partners