Adding a Resource in Global change

2 replies [Last post]
Andi Sydenham
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 31 Oct 2003
Posts: 5
Groups: None
Can any one tell me how to add a new resource to every activity. Some of the activities allready have resource assigned
Thanks Andi

Replies

A D
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Its straightforward and simple,

Go to Global Change,

Give the Filter criteria in the IF statement and then ADD the required RESOURCE in THEN Statement. No need, to develop any hard logic and break ur head.

Plz note, resource shud b defined previously in the dictionary.

Cheers,

Raviraj
Niek Zonneveld
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Well that’s fairly straightforward

Select all the activities (not the grouping bands); click on assign resources; select the resource you want add; click on assign.

H.T.H.