updating the baseline??need help

A
amit parmar 👤 Member for 19 years 4 months
A
A D 👤 Member for 19 years 1 month

Hi amit,



If you dont have baseline program saved, then copy the updated project and then do the following



Go to Global Change and put



If AS Is Greater Than "Baseline date"

Then

AS = " "

AF = " "

PCT = = o



This will definitely help you



Somebody has given this post before, please check the previous links. You may get some good stuff.



Cheers,



Raviraj

A
Ashraf Jahangeer 👤 Member for 19 years 2 months

Hi Amit,



I want to understand, dont you have a baseline schedule in place? Which is usually the case, we have a baseline and we have the live updated schedule.



If the answer is no then you can copy the live project and make a baseline (target). It will be bit of manual work to modify the updated project rsources and dates etc. Let us know the specific places where you face problem modifying the baeline manually.





Regards,





Ashraf

Featured Partner

Top Posters

Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts

Our Partners