updating the baseline??need help
Forum Sponsor
Top Posters
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Hi amit,
If you dont have baseline program saved, then copy the updated project and then do the following
Go to Global Change and put
If AS Is Greater Than "Baseline date"
Then
AS = " "
AF = " "
PCT = = o
This will definitely help you
Somebody has given this post before, please check the previous links. You may get some good stuff.
Cheers,
Raviraj
Hi Amit,
I want to understand, dont you have a baseline schedule in place? Which is usually the case, we have a baseline and we have the live updated schedule.
If the answer is no then you can copy the live project and make a baseline (target). It will be bit of manual work to modify the updated project rsources and dates etc. Let us know the specific places where you face problem modifying the baeline manually.
Regards,
Ashraf