Any help Mario??
Regards.
Thanks Mario,
I was thinking about create a schedule showing drawings as activities - with resources, link with the file etc - and creating new activities when new revision were requested by the costumer. Thus I could manage the time that each drawings would be leading to be ready, which drawings that would be suffering more revisions, which designers would be overloaded, which not, to measure productivity etc.
What do u think about that??
Thanks and regards.
Marcio Eduardo.
I would like to know if that is possible, positive and negative points etc.
Thanks.