Use Tools-> Graphic Reports-> Resource & Cost-> RC03 commulative and Monthly Cost. Change the date on the date tab and resource selection should be EQ ????????????
That will use all resources define on your projects.
I got it what u explained in ur last post. But same thing I want to generate from Tools>Graphic Reports>Resource & Cost>.
But when I m going to resource selection which is > Group if = EQ > Low Value Resource = My resource what I assigned > after selection of dates, curves etc. when I m running it is showing just periods or nothing.
Like what I have said, Ctrl+F7, This will display Resource Profile histogram and S-Curve.
On the Resource Profile dialog box under resource select Total and click Display. Under Display tick Cost and it should display cost S-Curve and histogram.
wht i did i want to explain, i add one resource name cost and pick all activities and apply resource assignment. Than i pick each activity and assign its cost from Budget > Budget Summary > Budget Amount under Cost Catogery.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Irfan,
Use Tools-> Graphic Reports-> Resource & Cost-> RC03 commulative and Monthly Cost. Change the date on the date tab and resource selection should be EQ ????????????
That will use all resources define on your projects.
Thanks for reply Rodel,
I got it what u explained in ur last post. But same thing I want to generate from Tools>Graphic Reports>Resource & Cost>.
But when I m going to resource selection which is > Group if = EQ > Low Value Resource = My resource what I assigned > after selection of dates, curves etc. when I m running it is showing just periods or nothing.
So pls can u help me again……
Thanks……..
Irfan,
Like what I have said, Ctrl+F7, This will display Resource Profile histogram and S-Curve.
On the Resource Profile dialog box under resource select Total and click Display. Under Display tick Cost and it should display cost S-Curve and histogram.
thanks rodel,
wht i did i want to explain, i add one resource name cost and pick all activities and apply resource assignment. Than i pick each activity and assign its cost from Budget > Budget Summary > Budget Amount under Cost Catogery.
But these costs not coming in my resource Curve.
Pls tell me how to generate S-Curve..
thanks,,,
Irfan,
Ctrl + F7 or View-> Resource Profile or click the icon Resource/Cost Profile
That will show Profile and S-curve in P3.