Removing the majority of links from an existing plan

2 replies [Last post]
S Stuart
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 8
Groups: None
Does anyone know of an easy way of removing all relationships (apart from a few select activities) from a plan of around 1000 tasks. At the moment it looks like going through every activity one by one and removing the links. Export/Import through excel is not an option because of the risk to data integrity.

Thanks in advance.

Seb

Replies

Paul Harris
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
There is no risk to the integrity of data using the P3 import function as long as your data is correct. There is a technical article on my web site that explains how to import through Excel, but always back up you file before commencing.

To delete all the relationships in a P3 project I usually delete the ***REL.P3 and replace it with a file from a project that has no relationships and rename as required.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Pranab Kumar Deb
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291