Fixing the Late Finish Date in P3

1 reply [Last post]
Ranilo Asiao
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 May 2004
Posts: 11
Groups: None
During updating, how to fix the latest Finish date eventhough the early finish date already passed the completion date but the late finish date will still be on time and at completion date?

Replies

Anoon Iimos
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it is because you have negative floats and constraints and the activity-progress is going out of sequence, you have options for scheduling, retained logic and progress override - you can play with it